In short

  • Type in how long the water took to drop in each test hole.
  • It works out the Vp figure, tells you if a drainage field can work, and how big it needs to be.
  • Uses the method and formula in Approved Document H2 for septic tanks.
75% full 25% full 150mm: time it 300mm square Dig to 300mm belowthe drainage pipe depth
Fill to 300mm and let it drain overnight. Next day, refill to 300mm and time the drop from 75% full to 25% full.
1. How long did each test take to drop 150mm?

Approved Document H says test at least 3 times, using at least 2 holes. Leave a row at 0 if you didn't do it.

Test 1
Test 2
Test 3
2. How many people will the septic tank serve?
people
3. Trench width

Approved Document H allows trenches 300mm to 900mm wide.

Tank Chamber Trench length Continuous loop. 2m of undisturbed ground between trenches. No steeper than 1 in 200. Pipe at least 500mm deep.

Where it can go (H2 1.27)

  • At least 15m from any building.
  • At least 10m from any watercourse or permeable drain.
  • At least 50m from a borehole, well or spring used for water, and not in a Zone 1 groundwater protection zone.
  • Also check the general binding rules and our rules checker.

Where this comes from

  • Approved Document H2 paragraphs 1.34 to 1.37: the test hole, the overnight soak, timing the drop from 75% to 25% full, and Vp = time in seconds ÷ 150. Take the average of at least 3 tests.
  • Paragraph 1.38: a drainage field should only be used when the average Vp is between 12 and 100.
  • Paragraph 1.44: floor area of the trenches, At (m²) = number of people × Vp × 0.25. Trench length = floor area ÷ trench width.
  • Paragraphs 1.40 to 1.43: trench width 300 to 900mm, 2m between trenches, pipe at least 500mm deep, laid no steeper than 1 in 200, inspection chamber between tank and field.
  • This formula is for septic tank effluent. Treatment plants are sized differently (see BS 6297): ask the plant maker or your designer.

Guide only, not a certified design. Figures from Approved Document H (2015 edition). Building control, or your designer, has the final say. Nothing you type here is sent anywhere.